Concurrent delay can be defined as situation where two or more independent delays falling under "employment risk" and "contractor risk" occur together and affect the project completion date.
They are an important part of claims management since both the contractor and the employers use the concurrency shield as a way to defend delay claims. Where contractors use it to defend any delay damages, employers can use concurrency as a way to avoid paying compensation for prolongation to contractors.
Concurrent delays have a reputation of being difficult to prove and analyze. In case the employer and contractor concurrently delay the work, responsibility cannot be attributed to a certain party and hence cannot be shared. In such situations, delay experts, having multiple years of experience are consulted, and they're are able to assess the delays and the right way to proceed with delay claims.
Project delays may result in numerous changes within the project form late completion to the need for acceleration and even contract termination. Depending upon the cause of the event, when a party suffers damage, the other party should compensate for the damage.
In successful concurrent delay claim practices, the following aspects need to be considered
In an attempt to acquire compensation for the time and cost incurred, the practice requires parties to be knowledgeable about the delays. The party that suffers damage should be able to recognize the delayed event when it happens, the damage it incurs, and the parties that are responsible for it.
In case the contractor is responsible for causing delay, and it has resulted in the extension of the project completion date, contractors shall be paying delay damages to the employer which are reasonable estimates premade in case of losses of the employers most likely to be incurred if the project is delayed.
In case the contractor suffers any delay, and the employers are at fault, the contractor is entitled for EOT and also the payment of any costs incurred and the profit. .In case the delay was caused due to reasons both parties couldn’t control such as the discovery of fossils or weather conditions the contractors may be entitled to the costs incurred but not the profits.
Claims that are relevant to time are often difficult form the time of preparation to evaluation. Time-related claims need to be resolved using three aspects including; liability, causation and damages. The process of claims management consists of 5 stages briefly discussed below:
In case of a concurrent delay where both the contractor and employees are responsible for delaying the critical path of the project, determining who caused the delays may become difficult. The consequences and impacts should be apportioned among the two parties depending upon their contributions and should be able to answer the questions below:
Compensation amount and delay damages are pronounced depending on the entitled apportionment for the extension of time.
In case of several delays affecting projects, no rules govern the prioritization of the delays, and all cases need to be judged based on their own. This is one of the reasons why apportionment methods should be identified based on the circumstances.
In case a decision cannot be reached, and parties decide on involving the courts, Delay experts are referred to, to determine the type of delay, parties at fault and how the parties should proceed.